The detailed design of the Padma Multipurpose Bridge is being delivered by a team of international,
Padma Multipurpose Bridge
The detailed design of the Padma Multipurpose Bridge is being delivered by a team of international and national consultants headed by AECOM.[20][unreliable source?] The team comprises AECOM, SMEC International, Northwest Hydraulic Consultants[21] and ACE Consultants, with additional assistance from Aas-Jakobsen and HR Wallingford
A key feature of the detailed design was the integration of Bangladesh counterparts into the design team, which allowed the successful training of a significant number of Bangladesh personnel in all aspects of the project and the subsequent transfer of the high level of technology involved in this large, complex project.
- Main bridge
- River training works (RTW)
- Janjira approach road & selected bridge end facilities
- Mawa approach road & selected bridge end facilities
- Service area - 2
- Resettlement
- Environment
- Land acquisition
- CSC (main bridge & RTW)
- CSC (approach roads & service area - 2)
- Engineering support & safety team (ESST
- Contractor: China Major Bridge Engineering Co. Ltd, China
- Contract period: 4 years + 1 years (defect liability period)
- Contract cost: BDT: 12,133.39 crore
- Date of work order: 26 November 2014
- Date of completion: 10 December 2020
- Physical progress of work: 100%
River training works 14 km (8.7 mi) length:
- Contractor: Sinohydro Corporation Limited, China
- Contract period: 4 years + 1 years (defect liability period)
- Contract cost: BDT: 9,400 crore
- Date of work order: 31 December 2014
- Date of completion: 30 June 2022
- Physical progress of work: 100%
Janjira approach road & selected bridge end facilities 10.50 km (6.52 mi) length:
- Contractor: AML-HCM JV
- Contract period: 3 years + 1 year (defect liability period)
- Contract cost: BDT: 1097.40 crore
- Date of work order: 8 October 2013
- Date of completion: 31 October 2016
- Physical progress of work: 100%
Mawa approach road & selected bridge end facilities 1.50 km (0.93 mi) length:
- Contractor: AML-HCM JV
- Contract period: 2.5 years + 1 year (defect liability period)
- Contract cost: BDT: 193.40 crore
- Date of work order: 27 January 2014
- Date of completion: 31 July 2017
- Physical progress of work: 100%
Service area-2:
- Contractor: Abdul Monem Ltd
- Contract period: 2.5 years + 1 year (defect liability period)
- Contract cost: BDT: 208.71 crore
- Date of work order: 12 January 2014
- Date of completion: 31 July 2017
- Physical progress of work: 100%
Resettlement:
- Total additional grant: BDT: 645.95 crore (up to September 2019)
- Total no. of plots: 2752
- 2418 plots handed over to the PAP (up to September 2019)
- Date of work order: 1 June 2009
- Date of completion: 30 June 2020
Environment:
- Total no. of trees planted: 1,69,957
- Date of work order: 1 June 2009
- Date of completion: 30 June 2021